Thionville – France
Last weekend the launch phases of the fourth project sequence were held in Thionville (France).
On this project we have developed on behalf of BIT S.p.A. the Detailed Design of the metal decks and the Detailed Design of the lifting and launching equipment.
The work of art, intended to implement the ring road intended for public transport towards the Thionville railway station, consists of two statically independent metal decks which develop from the C1 abutment to the P2 pier (curved section on the railway station side, assembled with lifting from below, spans….) and from pier P2 to abutment C7 (straight section on the side opposite the railway station, assembled with point launch from abutment C7, spans….).
Both decks are made with four core metal caissons